Do not start with data. Start with the methodology decisions and a cleaned register. Migrating a bad spreadsheet produces a bad platform faster.
Excel workbook
Run it against a real committee date. If the pack cannot come from the platform that cycle, the parallel run was theatre. Agree in writing the date the shadow spreadsheet is deleted, and put that date in the plan.
Name a first-line owner for the pilot area. If second line pilots on their behalf, you have learned nothing about adoption.